Water Line

Here are details about the materials needed.

  • 2 Masons @ $15/day X 15 days = 600.00
  • 4 workers @ $ 8/day X 15 days = 480.00
  • Transport/Supervision Fees + Ticket/3 days = 400.00
  • 6 truck of sand @ 200.00us$ = 1,200.00
  • 3 truck of gravel @ 250.00us$ = 750.00
  • 100 bag of ciment @ 8.50us$ = 850.00
  • Iron 1/2: 20 @ 12.00 us$ = 240.00
  • Iron 1/4: 20 @ 3.00 us$ = 60.00
  • Branch : 12 @ 3.50 us$ = 42.00
  • Transportation material (2 @ 200.00 us) = 400.00
  • from jeremie to castaches) 5,022.00
  • 10% misc. 502.20

TOTAL NEEDED 5,524.20 US$